Our construction team is making moves at the Pier 4 site. The following video captures an excavator removing soil to make way for the condominiums’ foundation. Our team has poured 2,300 cubic yards of concrete to line the building’s base to date, with another 3,200 cubic yards set to pour in mid-October 2016.

Next up, we are dismantling the granite sea wall along the east side of the Pier 4 site as we prepare to pour its new concrete footings, and installing cross bracing on the north side of the site to accommodate our next excavation.